geniusfull.blogg.se

Crane lift plan method statement
Crane lift plan method statement








crane lift plan method statement
  1. #Crane lift plan method statement full#
  2. #Crane lift plan method statement code#
  3. #Crane lift plan method statement free#

Be particularly cautious around powerlines. Inspecting and maintaining the crane regularly as prescribed by both the owner and manufacturer.īeing aware of any site conditions that could affect the crane operation. To calculate or determine the crane’s actual net capacity for every possible configuration of the machine. The operator must understand the correct meaning of all notes and warnings and be able Having a thorough knowledge of the information contained in the crane’s operating manual.īeing familiar with the crane’s load chart. The operator must understand its functions and limitations as well as its particular operating characteristics. Crane Operator Operators should know the machine well. The Erectors shall be competent and have the necessary documentation showing that they have had formal training in the safe erection of Tower Cranes and provide certificates.ġ2. Plant Field Engineer Coordinate with the Project Manager and Technical Department for the location and dimension of Tower Crane Foundation prior the installation of Tower Crane. The Method Statement and Risk Assessment, the use of proper tools and equipment to maintain safety, certifications of equipment and their adherence to safety regulations, reporting of any unsafe work or stopping work that does not comply with ES&H procedures.Įxecutes and ensures that the process of climbing, dismantling, erection and commissioning are properly executed based on the safety rules of operation and as per manufacturer procedure.ġ0. Will be closely monitoring the site engineer’s strict implementation of HSE Engineer Ensure enforcement of safety procedures in accordance with the approved HSE Plan. They ensure safe environmental working conditions for all employees.Ĩ. Health, Safety and Environmental (HSE) Manager generally plan,Ĭoordinate and implement issues and directives within the organization. He shall respond to any emergency that may occur. Plant Safety Officer Ensures that the company safety procedures are applied accordingly and properly. In accordance with the Manufacturer Instruction, Site Safety Plan andĦ. The supervisor’s main duties are to make sure the Work is carried out Of the operation be it wind, balance, power, stoppages etc. The supervisor has overall charge and if he is not happy with any part

#Crane lift plan method statement free#

Supervisor will check that the crane components are complete and free from any damages that may have occurred during delivery. The Supervisor shall be well trained and have a certificate showing that he have had formal training in the safe erection of Tower Cranes.

crane lift plan method statement

#Crane lift plan method statement full#

Undertakes the full responsibility of the whole process of erection, Shall be present throughout the installation, commissioning and dismantling process of Tower Crane. Plant Manager Verify the overall readiness and perfection of the erection, commissioning and dismantling process. Logistic Manager Coordinate with all project teams to ensure the safe protection of working areas, arrange a clear route for removing parts and all related permits are obtain.ģ. Project Manager Responsible to arrange calculation of foundation design and the execution of all ground preparation, and provide consultant approval for foundation.Ģ. Prequalification for Supply, Installation and Commissioning of Tower Crane – xxxxxxxxġ. Tower Crane Isolated Foundation Reinforcement Aproved Shop Drawing – xxxxxx Structural Design Report- Tower Crane-xxxx

#Crane lift plan method statement code#

Testing & Commissioning for Earthing BondingĮarthing Bonding and Lightning Protection System,īS 7121 Code of Practice for Safe Use of Crane Installation & Testing of Earthing, Bonding & Lightning Protection – xxxxx Method Statement for Concrete Works, xxxxxxxxxxxx HSE Plan Health, Safety and Environment Plan HSE Officer Health, Safety & Environmental OfficerĬEMP Construction Environmental Management Plan HSE Manager Health, Safety & Environmental Manager This Method Statement for Tower Crane Installation defines the sequence and describes the control procedures to be followed including, Commissioning and Dismantling for Project – xxxxxxxxx. Supervision and Monitoring ArrangementsĪPPENDIX E: Permit to Work & Lifting PermitĪPPENDIX G: Inspection and Test Plan I. V.2.2 Erection Procedure (Free Standing 52.4 m) V.3 Commissioning Procedure V.2.1 Prelude to Erection (Free Standing Crane) V.2 Tower Crane Installation-Erection Procedures

crane lift plan method statement

Check Controls, Lifting Gear and Switches IV.1 Accessibility, Equipment Handling and Work AreaĬ. Complete template of Method Statement for Tower Crane Installation along with the related attachments can be downloaded here.Ħ.Duration, Phasing with the Subcontractors










Crane lift plan method statement